McCarthy Stone Gosforth

Project details

Project Size
- 9 weeks
- 29 apartments 2,615m2 GIFA
- No. Storeys: 3, 1,318 linear metres panels
Building Type
Retirement Living
Construction type
Light Gauge Steel Frame (LGSF)
City
Gosforth
Country
UK
Installation year
2023
Client
McCarthy Stone
Impact quote
Gosforth is McCarthy Stone’s first development under the new Remagin brand, following previous successful schemes carried out at Hexham and Maghull (working with the former Sigmat brand). We have worked with the Remagin management team on our previous schemes and have always successfully delivered a quality product ahead of programme, collectively taking the learnings from these schemes to improve the process going forward. The key to our collective success is early engagement and collaboration with the Remagin team and wider supply chain
Impact quote author
Iain Fleming, Divisional Construction Director, McCarthy Stne
Installation quote
Our relationship with McCarthy Stone continues to grow stronger as we recognise improvements and positive changes on each project we do together. The team at Gosforth demonsrated just how quick a light gauge steel frame (LGSF) scheme can come to life. We are thrilled to be a part of this journey as they fully embrace Modern Methods of Construction (MMC) and in particular the Remagin LGSF system
Installation quote author
Stephen Parker, Contracts Manager, Remagin

Project description

Our fifth McCarthy Stone retirement living project, delivered two weeks ahead of schedule Following previous successful projects in Hexham, Broadstairs, Warminster and Maghull, and as part of our agreed framework with our partners at McCarthy Stone, the Remagin team have delivered the fifth retirement living scheme in a record 9 weeks. Situated in the North East town of Gosforth, the development will provide 29 retirement living apartments.

Working collaboratively, and with early engagement at the heart of our partnership approach, the McCarthy Stone site team have embraced the significant speed advantages offered by LGSF construction. Having completed four successful projects to date, our team are now well under way with plans for the sixth McCarthy Stone project in Stafford, which is due on site in September. McCarthy Stone’s commitment to constructing 50% of their future homes using offsite methods shows no signs of slowing down, and the team here at Remagin are delighted to be on this journey with them.

McCarthy Stone Gosforth case study

McCarthy Stone Gosforth case study

Downlaod full McCarthy Stone Gosforth case study